Instructions
Instructions :
1.Open Services from the start menu on the PVS server.
2.Disable the Stream service and wait for about 2-5 minutes, so that the existing connections/ target device would be re-distributed on other PVS servers through Load balancing.
3.Verify from the PVS console that the PVS server has got 0 connection on it.
(To Rebalance Provisioning Server connections manually:
a.In the Console, highlight the Provisioning Servers to rebalance, right-click then select the Rebalance devices menu option. The Rebalance Devices dialog appears.
b.Click Rebalance. A rebalance results message displays under the Status column.
c.Click Close to exit the dialog.)
4.Migrate the PVS server from one datastore to another datastore from hypervisor.
5.Enable the Stream service on that PVS server and wait for connections to re-distribute again.
6.Repeat the same steps (1-5) for other PVS server's in the farm.