NetScaler Console -14.1 43.50: Scheduled 2 stage upgrade fails for NetScaler in HA.

NetScaler Console -14.1 43.50: Scheduled 2 stage upgrade fails for NetScaler in HA.

book

Article ID: CTX693358

calendar_today

Updated On:

Description

Upgrade Jobs fails for NetScaler when we configure scheduled 2 stage upgrade process from NetScaler Console. The jobs seem to create several subtasks that are failing. It completes upgrade on 1 NetScaler but does not upgrade the second one. This happens after upgrading the NetScaler Console to v14.1 43.50.

Resolution

The fix is done under the internal bug id NSADM-120068.  The code fix was done for this bug in the version 14.1.47.14+ version. 


Problem Cause

The problem was caused due to multiple task logs commands sent to the NetScaler devices.